Power shortfall

Grids and generation cannot deliver the electricity datacentres need.

Cuts off 79 boxes, 41 of 53 stages · slows 40 · Show on the map →

Hits directly

Signs

The IEA estimates around 20% of planned datacentre projects could be delayed. Transmission lines take four to eight years and gas turbine lead times run to several years.

What would soften it

Efficiency gains, on-site generation, and building compute where power already is.

Cut off 79

Slowed 40

Sources

  1. 01IEA: Energy and AI, executive summary